Bucks arena to be fully enclosed by next week


Milwaukee Bucks president Peter Feigin and representatives from Mortenson Construction led a tour today of the Bucks arena construction site to show its most recent progress including the atrium, installation of inner bowl ribbon boards and speakers, a mock box suite, and the arena’s facade. Feigin said the arena will be fully enclosed within a next week and its facade will reach completion in about two weeks. Construction of the 714,000-square-foot arena will reach completion in the fall of 2018. 